Applied Digital wins $5.4 billion AI lease; financing next
Applied Digital signed an 18-year lease for 150 megawatts of AI data-center capacity with an unnamed investment-grade hyperscaler. Financing is next.
Applied Digital has signed an 18-year lease for 150 megawatts of AI data-center capacity with an unnamed investment-grade hyperscaler. The contract is expected to generate $5.4 billion in revenue, but the company must secure project financing before completing the facility.
The lease lifts Applied Digital’s contracted revenue above $41 billion across the initial terms of its agreements. The new contract averages about $2 million per megawatt annually, compared with roughly $1.65 million for the 210-megawatt Delta Forge 2 lease announced in June. The figures average revenue over each lease’s full term, while construction and operating costs will differ by project.
Applied Digital shares surged Monday following the announcement. The stock remains about 70% below its year-to-date high. The company expects to begin delivering capacity under the new lease in the first half of 2028, subject to construction milestones, utility arrangements and regulatory approvals.
Applied Digital has funded the initial equity for the new project through its balance sheet and its partnership with Macquarie Asset Management. The company expects to complete the remaining financing for its Delta Forge 1 and Polaris Forge 3 projects in the first quarter of 2027.
The company also announced a $300 million bridge facility for its Delta Forge 1 campus in Louisiana. The loan matures in 364 days and carries an interest rate of the Secured Overnight Financing Rate plus three percentage points. Draws are permitted only when specified conditions are met.
The financing terms for these projects will determine the amount of lease revenue remaining after construction costs, interest payments and other debt service. Data centers require spending on power infrastructure, cooling systems and equipment before they begin generating rent.
About 75% of Applied Digital’s contracted revenue from initial lease terms now comes from investment-grade customers. A tenant with a strong credit profile can give lenders more visibility into the cash available for project debt repayment, subject to the company completing each facility on schedule and within budget.
The new lease carries higher average pricing than earlier agreements. The hyperscaler was not identified in the announcement.